Thursday, 18 June 2026

Wednesday, 17 June 2026

Wednesday 17/6

The photos below are courtesy of Geoff Lowe:
Oliver & Oliver fitting Dora's spark arrestor

Tuesday, 16 June 2026

Tuesday 16/6

Logan removing gardening waste from a waggon

Monday, 15 June 2026

Wednesday, 3 June 2026

Tuesday, 2 June 2026

Tuesday 2/6

Richard shunting stock to prepare for contractor's access to the storage shed site
(The steam loco is Cyclops, built by Hawtorn Leslie, rebuilt by Barclay)

Thursday, 28 May 2026

Thursday 28/5

Neil drilling buffer spacers for engineers' saloon 1173

Tuesday, 26 May 2026

Tuesday 26/5

Richard using No.2 to empty the Andrews House Colliery branch to clear space in MH yard

Thursday, 21 May 2026

Thursday, 7 May 2026

Thursday, 30 April 2026

Wednesday, 22 April 2026

Tuesday, 21 April 2026

Tuesday 21/4

Steve & Colin making a rack for storing logs at ET

Wednesday, 1 April 2026

Wednesday 1/4

Terry fitting a sign at Causey Crossing
(photo courtesy of Geoff Lowe)

Thursday, 26 March 2026

Thursday 26/3

The photos below are courtesy of Peter Weightman except as shown:
Mick setting up new machine guards for welding

Wednesday, 25 March 2026

Wednesday 25/3

Dismantling a bullhead section of MH 'loop' for plant access to sheet the new shed

Tuesday, 24 March 2026

Tuesday 24/3

Lewis continuing to repair the drive cover for No.13 point

Thursday, 19 March 2026

Wednesday 18/3

Roger & Martin refitting the platform railings in ET carriage shed
(photo courtesy of Geoff Lowe)

Tuesday, 17 March 2026

Tuesday 17/3

Dave re-establishing the fence around the gulley after drainage installation