Wednesday, 30 November 2011
Trackwork
We plan to replace some bullhead sections of the mainline currently on wooden sleepers with bullhead on concrete sleepers (CS1s). This will ease maintenance in areas where it is difficult to replace individual sleepers, interface well with adjacent sections, utilise materials from stock, maintain the axle loading, and give a better 'heritage' appearance than modern heavy flat bottom rail on F27 (or similar) sleepers.
Labels:
Maintenance,
Track
Tuesday, 29 November 2011
The Working Week Continues
On East Tanfield curve, Ken and Bill fix replacement sleepers while Vic tidies the side of the formation |
Labels:
Engineering,
Maintenance
Monday, 28 November 2011
Another Week Begins
In the workshop: Alec, Dave, hi-vis Walter, Jim and Ian discuss work for the day, then get down to this.
Labels:
Engineering
Sunday, 27 November 2011
Pink feather boa on No.6
David and Steve pose with their pink feather boas, as part of the Guiness book of Records attempt on The World Wide Scavenger Hunt |
Labels:
Events
Saturday, 26 November 2011
Friday, 25 November 2011
North Pole Express Preparations
New helper Donna is seen posing on Saturday's locomotive, Twizell, which will be hauling trains to the North Pole |
Labels:
Events
The North Pole Awaits
Tomorrow sees the start of 5 weekends of North Pole Expresses. Trains on Saturday 26 Nov will be hauled by Twizell, first train at 11.20 and last at 2pm from East Tanfield, heading for the North Pole where Santa will greet everyone in his grotto. (There are additonal set up and set down trains outside of these times, and No.6 will be on standby.) All trains in December are fully booked - there are a few seats available on 26 & 27 Nov.
Colin and Matthew with xmas tree at the North Pole (photo courtesy David W) |
Labels:
Operations
Thursday, 24 November 2011
Various
Rubbish in, rubbish out, in preparation for catering disposal and firing the North Pole Expresses which start this weekend |
Labels:
Engineering
Wednesday, 23 November 2011
Tuesday, 22 November 2011
Monday, 21 November 2011
Engineering
I'm hoping that by now readers will know the sequence for resleepering track, so if anyone wants to test their knowledge practically, they would be most welcome to join in ....
The ballast in areas of Andrews House station west platform road was dug out yesterday thanks to the youth team, but everything was left intact because the line was in use (with the usual 5 mph limit).
Remove chairs and old sleepers ..... (the team are Mark, Phil, Malcolm, Malcolm and me) |
Labels:
Engineering
Sunday, 20 November 2011
Today's Trains
Renishaw Ironworks No.6 will be the loco for trains at 11, 12.30, 2 and 3.30 from Andrews House station.
Ian starting the FTR (fitness to run) examination ..... |
Labels:
Operations
Saturday, 19 November 2011
Information
1. TR Co shareholders - there is an open meeting with the board on Sunday at 9.30 am in the bait room.
2. This blog does not enable comments to be made against posts. To write about the railway, try Facebook (eg http://www.facebook.com/pages/Tanfield-Railway/108957235311) or the likes of Trip Advisor (http://www.tripadvisor.co.uk/ShowUserReviews-g190793-d1487934-r120451939-Tanfield_Railway-Gateshead_Tyne_and_Wear_England.html)
3. This Sunday No.6 will be hauling the last normal services of 2011 at 11, 12.30, 2 and 3.30 from Andrews House. The North Pole Express starts next weekend.
2. This blog does not enable comments to be made against posts. To write about the railway, try Facebook (eg http://www.facebook.com/pages/Tanfield-Railway/108957235311) or the likes of Trip Advisor (http://www.tripadvisor.co.uk/ShowUserReviews-g190793-d1487934-r120451939-Tanfield_Railway-Gateshead_Tyne_and_Wear_England.html)
3. This Sunday No.6 will be hauling the last normal services of 2011 at 11, 12.30, 2 and 3.30 from Andrews House. The North Pole Express starts next weekend.
Labels:
Other
Friday, 18 November 2011
Thursday, 17 November 2011
Wednesday, 16 November 2011
Tuesday, 15 November 2011
On Track Again
The Tuesday track gang have moved south to the end of Andrews House platforms, to take on replacement of the first section of timberwork of the point.
Crossing timbers under the nose section have to be moved by hand, because the crane cannot lift under the footbridge. |
Labels:
Civil,
Engineering,
Track
Monday, 14 November 2011
Sunday, 13 November 2011
Conservation
Some conservation work has been undertaken on locos in longer term storage.
James oiling the front tubeplate of Stagshaw |
Labels:
Loco
Today's Train
Cochrane will be hauling trains from Andrews House at 11, 12.30, 2 and 3.30.
The signalman making routine checks at the start of the day |
Labels:
Operations
Friday, 11 November 2011
Thursday, 10 November 2011
Wednesday, 9 November 2011
Today at Andrews House
Tuesday, 8 November 2011
The Tuesday Track Team
Monday, 7 November 2011
Track Work (cont)
Work continues on the second stage of retimbering the north point at Andrews House.
Lifting out the closure rails |
Labels:
Civil,
Maintenance,
Track
Public Rating for TR
Watch Trip Advisor about attractions in Gateshead to see where Tanfield lies compared with the Sage, Metro Centre, etc. This may be a comment on what there is to do in Gateshead (compared with Newcastle), rather than how good people find TR, but at least it shows public recognition. We seem to be important for locals and visitors to Gateshead, but need to develop and enhance our good points - we are mainly up against seven day a week attractions.
Labels:
Public
Sunday, 6 November 2011
Today's Trains
Cochrane will be hauling trains at 11, 12.30, 2 and 3.30 from Andrews House.
Steve and Sarah preparing Cochrane |
Labels:
Operations
Friday, 4 November 2011
Thursday, 3 November 2011
Wednesday, 2 November 2011
Track Maintenance
The north point at Andrews House is being resleepered and retimbered.
Removing rails from the old crossing timbers |
Labels:
Civil,
Engineering,
Track
Tuesday, 1 November 2011
A Fine Day
Vic levelling the site for North Pole Express temporary reception containers next to ET station foundations |
Labels:
Civil,
Engineering