Ian starting to cut fibre glass mesh for use as pit covers |
![]() |
Steve & Ian checking the invert into the man hole |
![]() |
Steve rechecking |
![]() |
Ian digging the trench for the field drain |
![]() |
Ian fitting feet & checking fit of pit covers |
![]() |
Jonny refitting No.2's LH slide bars |
![]() |
Steve following Ian's trench ..... |
![]() |
..... to check the depth for the drain |
![]() |
Dave levelling pea gravel in the base of the trench |
![]() |
Brian & Steve unwinding the pipe into the trench |
![]() |
Brian & Ian covering the pipe in pea gravel (which will duct water along & into the field drain) (photo courtesy of Dave Dixon) |
![]() |
Ian continuing his lengthy cutting task |
No comments: