Planned work matched the weather forecast of a sunny 17C - we got a misty damp 8C.
![]() |
Malcolm and Malcolm turning out a 90 lb/yd 30' BH rail |
![]() |
Malcolm and Ian turning in a 95 lb/yd 60' BH rail |
![]() |
Ian and Malcolm starting to remove the other leg |
![]() |
Graham, our boiler inspector, checking flanges and rivets in No.6's firebox, during its annual cold examination |
![]() |
Graham checking the firehole mouthpiece and rivets (Graham Morris Engineering Ltd, 07734560802) |
![]() |
Chris turning loco parts |
![]() |
Walter and Jim enjoying the crack |
![]() |
Alec on the pedestal drill |
![]() |
Peter checking fusible plugs against drawings |