Andrews House Relaying #4

Ethan, Dan, Dai & David screwing down chairs
The team cleaning rust from the chair seats
Steve & Antony turning in a rail
The team barring the last of a dozen rails .....
..... against the chairs .....
..... for Antony & Steve to turn in
Steve, Dai, me & Antony aligning sleepers with rail ends
(photo courtesy of David Reed)
Keying up .....
..... the first side
Steve following up with the fishplates
Ian lending a hand to bar the rail, chairs & sleepers .....
..... into place on the more difficult second side
Steve fitting the final fishplates
The view from Gibraltar Bridge tonight
This weekend Andrews House east platform only will be in use.   To be done - fully screw down the second rail to gauge, align to the west platform edge, ballast, pack to height, etc.   Whole process to repeat for the east road, although this is a bigger job including replacing sleepers, rail, nearly all fittings, ballast, pack, align, etc.