![]() |
Pouring rain outside, so Colin, Geoff & Bill tidy part of the woodwork shed |
![]() |
First cubic metre of 9.5 coming down the chute into the toilet foundations |
![]() |
Chris, Dave & Ian moving the concrete to the far end of the foundations |
![]() |
The next mixer full is poured |
![]() |
Colin bailing excess water as we level out the concrete to the height of the shuttering |
![]() |
Chris & Bill installing the upper reinforcement mesh |
![]() |
Dave & Ian working on a finished surface |
![]() |
More levelling (photo courtesy of Colin Gibson) |
![]() |
Colin watching Dave & Ian finishing the surface of the first layer |
![]() |
John has been working on the ring main & container lighting |
![]() |
Geoff spreading his green |
![]() |
Dave sawing shuttering for the second pour, the upper part of the foundations |
No comments:
Post a Comment