| Dennis, Dave, John & Geoff removing screws from the loop south point |
![]() |
| Ian & a fitter replacing a burst hose on the fork lift |
![]() |
| Removing tie bars |
![]() |
| The view southwards - the headshunt will also be moved |
![]() |
| Dave on the impact wrench, nearest the camera |
![]() |
| Preparing the switches to be lifted out |
![]() |
| Nigel & Dennis unscrewing the point lever |
Bait time, & Bob finds another creature in his bait box (it was a mouse last week)
![]() |
| Aligning sleepers, to be able to insert rail |
![]() |
| The rails are in, & being trimmed to length (AW No.2 is the first loco in the loop for a while) |
![]() |
| Bob & Nigel drill a rail end (Bill the drill was AWL) |
![]() |
| Aligning the next set of sleepers |
![]() |
| Turning another rail into the chairs |
![]() |
| Bob & Geoff keying |
![]() |
| Ian has cleared the point area of wood & metal |
![]() |
| Bob & Nigel at Causey Level Crossing on the return |