Search

Wednesday 9 March 2022

Starting Sunniside Sleeper Wall

Ian unloading the digger
Starting to unload sleepers
The first few sleepers are erected
(photo courtesy of Geoff Lowe)
Barry putting a kerb in place
(photo courtesy of Geoff Lowe)
Ian checking the sleepers are vertical
(photo courtesy of Geoff Lowe)
Ian scraping off undergrowh
(photo courtesy of Geoff Lowe)
The wall continues .....
(photo courtesy of Geoff Lowe)
..... over a tree root
(photo courtesy of Dave Dixon)
Ian moving south with the trench
(photo courtesy of Dave Dixon)
Barry clearing bricks
(photo courtesy of Dave Dixon)
Checking alignment
(photo courtesy of Dave Dixon)
Terry & Cameron attaching an alignment rail
(photo courtesy of Dave Dixon)

Filling in to keep the sleepers upright
Slinging .....
..... & lifting off packs of sleepers
Moving southwards
More packing, with 50 sleepers in place at the end of work today