Search this blog

Monday, 26 March 2012

Monday Work

Stripping out a BH panel under Gibraltar Bridge
Malcolm, Malcolm and Phil stripping out a
BH panel under Gibraltar Bridge
John repairing an electrical installation in Marley Hill shed
John repairing an electrical installation in Marley Hill shed
Dave working on vac fittings
Dave working on vac fittings
Jim has been working on Cochrane's crosshead slippers
Jim has been working on Cochrane's crosshead slippers
Malcolm slinging BH panels for removal
Malcolm slinging a BH panel for removal .....
Ian, Malcolm and Malcolm continue past Marley Hill signalbox
..... Ian, Malcolm and Malcolm continue
past Marley Hill signalbox .....
lifting the flat crossing of the Tanfield Branch (over the Bowes Railway)
..... lifting the flat crossing of the Tanfield Branch
(over the Pontop & Jarrow or Bowes Railway) .....
so that Vic can cross with the hired excvataor
..... so that Vic can cross with the hired excvataor .....
and begin to level the formation under Gibraltar Bridge
,,,,, and begin to level the formation under Gibraltar Bridge

There's plenty more work tomorrow and the rest of the week, reinstalling the new concrete panels, plus a good weater forecast, for anyone who would like to give a hand .....