 |
Unloading Vic this morning ..... |
 |
..... so that he can level the trackbed |
 |
Angela, Nigel and Rob placing the first panel today (more panels on the waggons behind the crane) |
 |
John & Nigel fishplating |
 |
Angela & Nigel slinging |
 |
Leaving the first empty waggon in Causey bay |
 |
Angela, Nigel and John placing another panel (with Vic clearing the trackbed further down) |
 |
Some slews are tight between trees |
 |
Rob, Angela, Nigel, John and panel at crossing #2 |
 |
How many fellers to remove a broken branch? |
 |
Angela, Rob & Nigel placing 15' panels,
with Ian in the crane |
There are 10 x 30' panels to go - 5 are loaded, so we aim to make 5 tomorrow. Then temporary short rails are to be changed for 60' lengths, followed by alignment and packing, plus a lot more ......