Jonny at work underneath No.49 |
Antony & Richard attaching fittings to 49's backhead |
Richard & Bobby fitting 49's main steam pipe
(photos courtesy of Antony Walker)
David sanding van 111's door before painting (photo courtesy of Bob Payne) |
Works train heading for Tanfield |
One of a large number of Durham countryside volunteers working on Causey footpaths |
At East Tanfield, Ian checking clearances ready for pouring concrete tomorrow |
Later in the day, a problem is fixed before tomorrow's concrete delivery |
Geoff touching up paintwork of ET station |
Kevin & Nigel ..... |
..... & George & Dave uncovering the platform foundations |
Steve floating a quarter ton CS1 into place |
Ian checking levels |
Steve & Nigel drilling a closure rail at the shed entrance |
Ian & Kevin scooting the other closure into place |
Steve keying while Nigel & Geoff keep the rail seated in the chairs |
Ian removing temporary runway rails |
First railway vehicle in the shed is the 8 wheel bogie, the Husky being the inaugural loco |