| The view from above |
![]() |
| One of the old sheets being removed ..... (photo courtesy of Dave Dixon) |
![]() |
| ..... & slid down the roof (photo courtesy of Dave Dixon) |
![]() |
| Ian & Ian operating from the basket |
![]() |
| Barry & Rob stacking the used sheets (photo courtesy of Dave Dixon) |
![]() |
| The sheets are short because these are all we had, & in temporary use (photo courtesy of Dave Dixon) |
![]() |
| The ground team wait for the ridge support to be slid down |
![]() |
| Sheet removal continues as the ground team spring into action |
![]() |
| Another sheet being slid down |
![]() |
| Last few pieces being unscrewed |
![]() |
| Checking around the chimney |
![]() |
| Ian fastening down a new sheet |
![]() |
| Rob, Dave & Barry loading another sheet ..... |
![]() |
| .....to be delivered through the purlins |
![]() |
| Trimming around the chimney ..... |
![]() |
| ..... in close up (photo courtesy of Dave Dixon) |
![]() |
| Dave & Barry resetting the tower after partial dismantling to move it past a truss |
![]() |
| More cutting to fit another sheet around the chimney ..... |
![]() |
| ..... then align & screw down |
![]() |
| 85% of the new sheets fitted to the north side of the main roof |