| Richard painting metalwork for the lantern roof |
![]() |
| Moving the few remaining roof sheets into storage |
![]() |
| Mick fitting a monkey tail to No.6's safety valves ..... |
![]() |
| ..... & rigging them for a pressure test |
![]() |
| Brian discussing No.2's footplate with Malcolm ..... |
![]() |
| ..... who continues drilling |
![]() |
| Dennis grinding excess weld from HC 38's bunker |
![]() |
| Barry marking ..... |
![]() |
| .....& removing excess roof sheet after it's been cut away |
![]() |
| Ian & Steve working on the sheeting ..... |
![]() |
| ..... & completing that part of the job |
![]() |
| Richard & Dennis freeing rusted threads on a tie bar for the lantern |
![]() |
| Ian mixing mortar ..... |
![]() |
| .... with which Steve points ..... |
![]() |
| .....the inside of the front gable |
![]() |
| Cleaning the scissor lift afterwards |