Dave continuing to fit floorboards to the platform in East Tanfield carriage shed |
Each board is cut to length to suit the joists, which are at approx 400 mm centres |
Rob & Colin are fitting the boards to the next row - note there aren't many boards remaining |
We've got to fit one full length at a time, because we may not be able to buy the same width board next time - we're exhausting local supplies |
Another run being finished |
Last row for the day, until new supplies arrive |
The mob meets in the middle |
Ian surveying the work so far - floorboarding is 75% complete |