Search this blog

Thursday, 19 July 2018

More Floor

Dave continuing to fit floorboards to the platform in East Tanfield carriage shed
Each board is cut to length to suit the joists, which are at approx 400 mm centres
Rob & Colin are fitting the boards to the next row - note there aren't many boards remaining
We've got to fit one full length at a time, because we may not be able to buy
 the same width board next time - we're exhausting local supplies
Another run being finished
Last row for the day, until new supplies arrive
The mob meets in the middle
Ian surveying the work so far - floorboarding is 75% complete

No comments: